Garfield
OBJECTIVES
Inspection of approximately 2 miles of sewer and associated manholes
SCHEDULE
Majority of inspection work complete. Some sporadic work may be ongoing.
Locations
Garfield, New Jersey
Updates
PVSC consultant CDM Smith and contractor RedZone Robotics will be inspecting sewers in Clifton, Garfield, Harrison, Kearny, Newark, North Arlington, Passaic, and Paterson from mid-October through mid-November, 2018.
As of early April 2017, sewer inspection work is largely complete in Belleville, Nutley, East Rutherford, Wallington, Paterson, and Garfield. Inspection crews may be returning for short durations to finalize inspections of special structures.
PVSC consultant CDM Smith and contractor RedZone Robotics will be inspecting manholes and sewers in Garfield and Wallington beginning March 17, 2017 and lasting through March 31, 2017.