Lyndhurst
OBJECTIVES
Inspection of approximately 2,600 feet of sewer and associated manholes
SCHEDULE
Inspections starting April 10 and continuing through April 14, 2017.
Locations
Lyndhurst, New Jersey
Inspection of approximately 2,600 feet of sewer and associated manholes
Inspections starting April 10 and continuing through April 14, 2017.
Lyndhurst, New Jersey
Sewer inspection work is now largely complete in several towns, but inspections continue in Passaic, Clifton, and Newark. Construction around Schuyler Ave in Kearny is expected to conclude in mid-May.
PVSC consultant CDM Smith and contractor RedZone Robotics will begin manhole and sewer inspections April 7, 2017 in Lyndhurst, North Arlington, and Rutherford.