Harrison
OBJECTIVES
Inspection of approximately 4 miles of sewer and associated manholes
SCHEDULE
Inspections starting March 22 and continuing through mid-April, 2017, with additional inspections occurring May 4th and 5th.
Locations
Harrison, New Jersey
Updates
PVSC consultant CDM Smith and contractor RedZone Robotics will be inspecting sewers in Clifton, Garfield, Harrison, Kearny, Newark, North Arlington, Passaic, and Paterson from mid-October through mid-November, 2018.
Sewer inspection work is now largely complete in several towns, but inspections continue in Passaic, Clifton, and Newark. Construction around Schuyler Ave in Kearny is expected to conclude in mid-May.
PVSC consultant CDM Smith and contractor RedZone Robotics will begin sewer inspections in Harrison beginning March 22, 2017. Inspection work will continue through mid-April, 2017.